Work Items Selections
In the following sections click the check-box next to each work item
that the company wishes to be
considered for during the bidding process:
Excavation & Grading Work Items
Site Clearing -- Site clearing includes cutting, and removal
from property, or grinding of, all required trees and brush.
Site Survey -- Site survey includes staking for rough grade, parking areas, and excavation requirements
Rough Grade -- Includes site leveling, parking / garage access
Footer / Foundation Excavation
Footer / Foundation Backfill
Final Grade -- Includes installation of road base, or other to be determined material, in
driveway, parking, and garage access areas.
Concrete / Insulating Concrete Forms (ICF) Work
Items -- All foundations, load-bearing walls, shear walls, stem walls, lintels, retaining walls, etc. will be poured using
Insulating Concrete Forms
(ICF). All non-ICF concrete work shall include placement and removal of required forms.
This item will include providing, or subcontracting for, any required
installation equipment and/or labor (e.g.-pump truck)
Footers
Foundation
Interior Slab -- Interior slabs will be broom finish.
Exterior Slab -- Exterior slabs will be stamped/colored
Faux-Crete
Faux-Crete -- Stamping and coloring
work only
Design ICF
Furnish ICF
Install ICF -- This
item may optionally include subcontracting for concrete pour of the forms.
Structural Insulated Panel (SIP) Work Items
-- SIPs will be used for all exterior walls, and roof of main structure. SIPs
may require interior or exterior cladding.
Design SIPs
Furnish SIPs
Install SIPs -- This item will
include providing, or subcontracting for, any required installation equipment
and/or labor (e.g.-crane, boom, etc.)
Trusses Work Items -- Trusses for the
Garage, Workshop, and Mechanical Room portion of the building.
Design Trusses
Furnish Trusses
Install Trusses -- This item will
include providing, or subcontracting for, any required installation equipment
and/or labor (e.g.-crane, boom, etc.)
Sub-Floor Work Items -- Sub-Flooring for the
Main Floor & Loft will be Engineered I-Beam Joists with T&G CDX
Sub-Floor
Furnish Joists & Sub-Flooring
Install Joists & Sub-Flooring -- This
item will include providing, or subcontracting for, any required installation
equipment and/or labor (e.g.-crane, boom, etc.)
Roofing Work Items -- All roofing will be hi-rib steel, exposed fastener, "Pro Panel" or
equivalent
Furnish & Install Roof Deck (Garage & Workshop) -- This
item will include providing, or subcontracting for, any required installation
equipment and/or labor (e.g.-crane, boom, etc.)
Furnish & Install roofing and underlayment (Entire Structure) --
This item will include providing, or subcontracting for,
any required installation equipment and/or labor (e.g.-crane, boom, etc.)
Exterior Stucco Work Items -- Most exterior surfaces will be stucco. There will be two tones utilized.
Furnish underlayment and stucco
Install underlayment and stucco
Windows/Glazing Work Items -- All windows & glazing will require supplier obtained measurements
prior to procurement
Design all windows/glazing
Furnish all windows/glazing
Install all windows/glazing
Interior Drywall / Plaster Work Items
Furnish / Install interior drywall where required
Furnish / Install cement backer board where required
Install plaster or faux-plaster finish on drywall
Fresh Water Supply System Work Items -- Preliminary water system design is depicted at
www.fiaranch.com or a paper copy can be furnished upon request.
Furnish / Install well pump
Furnish / Install static tanks/cisterns
Furnish / Install water supply piping -- Including
required trenching and backfill.
Furnish / Install water supply electrical
Furnish / Install pressure system
Waste Disposal Systems Work Items -- Septic system will have separate gray & black water treatment
Install gray water system
Install French Drain system
Install black water system
HVAC System Work Items -- The
HVAC System will be multi-load, multi-temperature, multi-fuel source. Preliminary water system design is depicted at
www.fiaranch.com or a paper copy can be furnished upon request.
Design
HVAC system
Furnish HVAC system
Install HVAC system
Administrative Work Items
Project Management services -- Provide
on-site project management for the project.
Consulting services -- Provide consulting services regarding
installation, usage, and maintenance of products utilized for the project.
Training services -- Provide training services regarding
installation, usage, and maintenance of products utilized for the project.