|
A Short Stint Until The Holiday Break
Mother Nature has not let up. So
not a lot accomplished since the last update. We were chased off
the mountain a couple of times by storms, including, by a blizzard about
a week before I planned to shut down for the holidays. Decided we
better shut down early, or we might wind up spending Christmas in the
construction office.
But we got a few things accomplished.
But first, as always, the farm report.

One of the herds of wild horses wandered up the ridge,
and were hanging out a couple of hundred yards from the property.
And the weather report.

So........ what happens when you do not plan your steel
roof for 120-140 mph winds? That will be a topic of discussion
with the roofing manufacturers I am considering. This place was in
the path of the hurricane winds we had last month.
Now back to work. What little there
was between storms.

Formed the wall curbs and the water pump(s) platform in
the mechanical storage building.

Time for concrete slabs. Poured the workshop and
mechanical/storage building wall curbs first.

The next day, the
forms are stripped from the wall curbs and pump platform to pour the slab in
the mechanical/storage building.

The outbuilding slabs are power-troweled to a hard trowel
finish.

And just in time for, guess what? Yup! Got
the slabs all covered with curing blankets, and packed up and left as
the next storm was moving in. They are still sitting under the
blankets and will be like that until the wall and truss packages are
delivered after the first of the year.

In the mechanical room of the main house, the interior
ICF foam is stripped away from the concrete foundation wall. This
is necessary so that the conduits that come out of the slab in that room
can come up near the wall curb and not 2+ inches away from it.

I was planning on using a liquid rubber waterproofing on
the exterior of the house foundation. But, it needs 24 hours above
freezing to cure, and storm delays caused the
temperature to catch up. So I to use roll water-proofing instead.
Temperature is still too cold for it to stick well to the foam, but on
this sandstone mountain, it really isn't necessary to start with.
Just provides some protection to the ICF foam. Not really worried
about any kind of water infiltration.

After another storm, we started backfilling the main
house foundation. We got about a foot or so from the top before we
ran out of dirt that was not filled with "permafrost". So the main
house foundation will sit until spring before any further work is done
on it.
Coming Up
The next 2-3 months will be spent working on the
out-buildings. And that is where we will pick things up after the
holidays.
|